Furnace drain at Noelle + von Campe
As part of the general repair of furnace 4, the furnace drain took place at the Noelle + von Campe plant in Boffzen on April 29, 2025.
Glass melting technology specialist HORN is equipping the repaired environmentally friendly furnace 4 with the latest, low-emission technology and is responsible for the complete detailed planning of the refractories as well as the steel construction for the furnace, distributor and five forehearths.
In this project, HORN experts are carrying out the furnace drain, demolition, the complete construction work for the refractory material, steel and equipment as well as the heating up.
The new regenerative end fired furnace is expected to be commissioned in July 2025.
20.05.2025, HORN Glass
printSollte der Inhalt oder die Aufmachung dieser Seiten fremde Rechte Dritter oder gesetzliche Bestimmungen verletzen, so bitten wir um eine entsprechende Nachricht ohne Kostennote. Ich garantiere, dass die zu Recht beanstandeten Passagen unverzüglich entfernt werden, ohne dass von Ihrer Seite die Einschaltung eines Rechtsbeistandes erforderlich ist. Dennoch von Ihnen ohne vorherige Kontaktaufnahme ausgelöste Kosten werden wir vollumfänglich zurückweisen und gegebenenfalls Gegenklage wegen Verletzung vorgenannter Bestimmungen einreichen.