HORN® secures Stoelzle Oberglas GmbH furnace order
In November this year HORN® received the order for the cold repair of furnace 2 for the Austrian parent plant in Koeflach.
This is a 93.75 m² end fired furnace with six forehearths for the production of container glass. In the future the plant will produce 270 tonnes of flint glass per day. The existing furnace will be enlarged by HORN® and equipped with new heating equipment and safety control. Furthermore, it will be equipped with a new melting boosting system, a new HVR® 700F-2P batch charger and further furnace equipment.
Shortly after the order was placed, the first video conference for coordination talks with Stoelzle Oberglas GmbH regarding the cold repair took place. At this point we wish all parties involved a successful and trouble-free project.
15.12.2020, Horn Glass Industries
printSollte der Inhalt oder die Aufmachung dieser Seiten fremde Rechte Dritter oder gesetzliche Bestimmungen verletzen, so bitten wir um eine entsprechende Nachricht ohne Kostennote. Ich garantiere, dass die zu Recht beanstandeten Passagen unverzüglich entfernt werden, ohne dass von Ihrer Seite die Einschaltung eines Rechtsbeistandes erforderlich ist. Dennoch von Ihnen ohne vorherige Kontaktaufnahme ausgelöste Kosten werden wir vollumfänglich zurückweisen und gegebenenfalls Gegenklage wegen Verletzung vorgenannter Bestimmungen einreichen.